Rolling out the smart queue piloted in the Al Malqa centre to all fourteen of the municipality's service centres: entrance screens, booking by QR code and from the municipality's app, and text messages with the expected time.
Methods applied
The method templates the team filled in. Browse the method template library
| Method | Template used | Completed template | Note |
|---|---|---|---|
| Lean startup | — | demo-initiative-158.pdf | لوحة نموذج العمل الخفيف لمرحلة التعميم. |
About this initiative
- Organisation
- Riyadh Region Municipality
- Delivered by
- Service Centres Department
- Sponsor
- نورة الدوسري
- Project lead
- تركي المطيري
- Team
- شهد الجهني, ماجد الشهري
- Started
- 13 Safar 1448 AH — 27 July 2026
- Target delivery
- 9 Ramadan 1448 AH — 16 February 2027
- Budget
- 380,000 riyals
Solution profile
- Solution maturity
- Trial version (since 13 Safar 1448 AH — 27 July 2026)
- Beneficiary segments
- Citizens, Residents
- Emerging technologies
- Internet of Things
- Innovation methodology
- Design thinking
- Idea source
- Innovation event
Progress
- Milestones
- 2 of 4 complete (50%)
- Targets
- Average achievement 64% (1 of 2 measured)
- Next reading
- 19/8/1448 AH — 27/1/2027
Implementation milestones
- Screens installed in six centres Completed 15/3/1448 AH — 28/8/2026
- Booking connected to the municipality's app Completed 2/5/1448 AH — 13/10/2026
- Front-desk staff trained in every centre Overdue — was due 3/5/1448 AH — 14/10/2026
- Live in all fourteen centres Due 9/9/1448 AH — 16/2/2027
Projects
Targets and impact
Not counted in the programme totals until the initiative is delivered. Achievement compares the latest reading with the expected value, from the baseline.
-
- Baseline
- 45 minutes
- Expected
- 20 minutes
- Latest actual
- 29 minutes
- Last reading
- 17/4/1448 AH — 28/9/2026
Next reading due 20/10/1448 AH — 28/3/2027 (read every 6 months).
Readings over time
Readings of “Average wait in service centres” over time — the numbers Reading date Actual value (minutes) Expected value 2026-08-20 34 20 2026-09-28 29 20 حسب نتائج التجربة في مركز الملقا.
People benefiting
Standard impact measure
Not measured yet: the achievement shows once a reading is entered.
- Baseline
- —
- Expected
- 52,000 beneficiaries
- Latest actual
- —
- Last reading
- —
Next reading due 19/8/1448 AH — 27/1/2027 (read every 6 months).
Beneficiary feedback
No feedback yet. If you use this solution, tell the team what works and what could be better.